Construction site at Metallimiehenkuja started in February
The construction site causing noise and heavy traffic in Otaniemi started in February.
The excavation will include pre-splitting drilling and blasting. The first test blasts will be carried out on Thursday of week 11 (March 13, 2025). The blasting times are 9:30–9:45 AM and 1:30–1:45 PM. The test blasts will define the schedule for the
Further high noise level work will continue according to the previously distributed schedule from February 3 to November 15, 2025, on weekdays from Monday to Friday between 7:00 AM and 6:00 PM, and, if necessary, every other Saturday between 9:00 AM and 5:00 PM. Regular construction work may also be carried out outside these time windows.
Pedestrians are advised to pay attention to heavy traffic near the construction site.
More information:
NCC Suomi Oy, Supervisor Jari-Pekka Valtonen, p. 010 507 51 (NCC switch)